Smithfield, NC - Johnston Regional Airport JNX – Tree Clearing
The project includes the clearing of Automated Weather Observing System (AWOS) critical areas which encompasses the removal of trees, clearing and grubbing. The project will be split into two (2) phases:
• Phase 1
o Clear tress for haul route and staging area.
o Establish temporary erosion control construction entrances and silt fence.
o Establish temporary haul roads.
o Clear trees in designated Phase 1 areas.
• Phase 2
o Establish timber mats in wetland and Swift Creek buffer areas.
o Clear trees in designated Phase 2 areas.
o Remove timber mats and replace with straw matting.
o Remove temporary haul roads.
o Perform seeding and mulching in disturbed areas.
o Remove temporary erosion control construction entrances and silt fences.