Jefferson, NC - Ashe County Airport - Perimeter Fencing

Ashe County and the Ashe County Airport are proceeding with the Perimeter Fencing Project which consists of installation of a new perimeter fence around the airport and clearing and grubbing adjacent to proposed fence locations. The overall scope of work for the project includes existing gate and fence removal, fence installation, a motorized sliding gate, an access control system, erosion and sediment control measures, and clearing and grubbing. The intent of this project is to provide bidding and construction of approximately 630 linear feet of fence and a proposed gate around the northwest hangar development.
            

 

    

Contact:   Denise Merritt
PreBid Date:   04/05/2022 10:00 AM
PreBid Info:   Ashe County Airport, Terminal Building. A site visit will be conducted after the Pre-Bid Conference.

Company:   AVCON, INC.
Bid Date:   05/03/2022 03:30 PM
Bid Info:   See Addendum #2
Sealed envelopes containing bid proposals shall be addressed to: Mr. Eric Payne, Airport Manager, Ashe County Airport, 639 Airport Road,Jefferson, North Carolina 28640
Envelopes must be marked “Bid Proposal – PERIMETER FENCING PROJECT and must have the bidder’s North Carolina contractor’s license number on the envelope.

Project Location: Jefferson, NC

Public Notes:
Questions about this project should be directed to:

J. Denise Merritt
Avcon, INC.
10115 Kincey Avenue, Suite 140, Huntersville, NC 28078
Phone:704-954-9008
Email:dmerritt@avconinc.com

Contractor shall meet the following bidding requirements:

• Contractors must be listed on the NCDOT Prequalified list as a bidder or Prime to bid on this project.
• Contractors, including subcontractors, must have a NC Contracting License pertaining to their discipline of work.
• Contractors, including subcontractors, must be prequalified by the NCDOT to perform the work pertaining to their specific scope of work in the contract. The prime contractor for the project must be prequalified by the NCDOT as a prime.
• Work codes for this project include, but are not limited to: 000200 CLEARING AND GRUBBING, 000866 FENCE INSTALLATION, 001605 TEMPORARY SILT FENCE, 001660 SEEDING AND MULCHING.
• Work code 00099 OTHER will not be accepted unless otherwise approved by the NCDOT or NCDOA that the work associated with that work code description for the contractor matches the work for the project.

The prequalified list of contractors can be found at: https://www.ebs.nc.gov/VendorDirectory/default.html

For more information about getting prequalified with the NCDOT, please visit: https://connect.ncdot.gov/business/Prequal/Pages/default.aspx

All Contractors are hereby notified that they shall have proper Contractor’s licenses as required by the state laws governing their respective trade in the state where this Project is located.

Bid security in the form of a bid bond equal to 5% of the total amount bid is required. Contract security in the form of 100% Performance and Payment Bonds will be required.

No bid may be withdrawn after closing time for the receipt of bids for a period of ninety (90) calendar days.

Written questions from prospective bidders will be accepted until April 8, 2022 at 5:00 pm. After that, no questions will be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

Notice is hereby given that the bid documents for this project contain a provision for participation by Disadvantaged Business Enterprise (DBE). This project has a goal of 0% of the total dollar value of the contract to be performed by DBE subcontractors. The DBE document contained within the specifications must be submitted with the bid and a 0% DBE participation indicated. Bids not containing this document are subject to disqualification.

Liquidated damages of $1,000 per day shall be assessed against the contractor for each day the contactor exceeds the contract time.

The maximum construction time allowed for the Project is 60 Consecutive Calendar. Permitting the Contractor to continue and finish the work or any part of it after the time fixed for its completion, or after the date to which the time for completion may have been extended, will in no way operate as a waiver on the part of the Owner of any of its rights under the contract.

ASHE COUNTY reserves the right to waive any informalities or irregularities in or reject any or all bids and to award or refrain from awarding the contract for the work, whichever is deemed to be in the Owner's best interest.